Illinois Rise IDOC Procurement

OACRA News & Policy Review Procurement & Market · Illinois
Open · SOQs Due Sept. 25 Corrections Infrastructure · Reentry · Justice Technology · Illinois
Illinois $1.1 Billion RISE IDOC Procurement Enters Vendor-Engagement Week

Illinois is advancing a $1.1 billion progressive design-build procurement for two new correctional facilities in Crest Hill, with vendor outreach and an RFQ briefing scheduled this week ahead of a September 25 qualifications deadline.

Published August 24, 2026 OACRA News & Policy Review
Aug. 24 procurement check The RISE IDOC RFQ remains open. CDB identifies August 26 for general contractor and vendor outreach and August 27 for the dedicated RISE IDOC RFQ informational meeting. Statements of Qualifications are due September 25, 2026 at 2:00 p.m.
Current status The Illinois Capital Development Board is seeking qualifications for one Progressive Design-Build Entity to deliver the RISE IDOC men’s and women’s facilities. Interested firms must satisfy applicable CDB prequalification requirements before submitting.

Illinois is moving a major corrections-infrastructure project into an active vendor-engagement period as the state advances its RISE IDOC procurement for two new multi-security-level correctional facilities in Crest Hill.

The Illinois Capital Development Board, in partnership with the Illinois Department of Corrections, issued the Request for Qualifications for CDB Project No. 120-000-078 on August 6, 2026. The project — Rehabilitation and Restoration Inside Safe Environments, or RISE IDOC — calls for a single Progressive Design-Build Entity to deliver new men’s and women’s correctional facilities in Will County.

The RFQ identifies $1.1 billion as the state’s estimate for the Progressive Design-Build contract amount. That figure is an estimate, not an awarded contract value.

Vendor engagement moves into focus this week

CDB has scheduled a general informational outreach event for contractors, subcontractors, engineers, architects, suppliers and professional-services firms on August 26 from 9:30 a.m. to noon in Crest Hill.

A dedicated RISE IDOC Progressive Design-Build RFQ informational meeting follows on August 27 from 10:00 a.m. to noon Central. CDB says the session will review the RFQ and include a question-and-answer period, with in-person and virtual participation available.

CDB previously identified August 24 as the date on or after which prequalified firms could submit Statements of Qualifications. The live procurement page states that interested firms must be prequalified before submission and advises that the prequalification process can take up to 45 days.

Procurement signal The RFQ itself was issued August 6. The current news point is the project’s movement into an active vendor-engagement period, not the opening of a newly issued solicitation.

Two multi-security-level facilities are planned

The RISE IDOC initiative calls for two new correctional facilities on IDOC property in Crest Hill.

The men’s facility is planned for approximately 1,500 beds, with infrastructure supporting future expansion to approximately 1,950 beds. The women’s facility is planned for approximately 800 beds.

Swipe horizontally to review the full table.

Project elementCurrent state plan
Men’s facility1,500 beds, expandable to 1,950
Women’s facility800 beds
Men’s preliminary areaApproximately 1.01 million square feet
Women’s preliminary areaApproximately 505,000 square feet
Delivery modelOne Progressive Design-Build Entity for both facilities

The RFQ describes rehabilitative and gender-responsive environments intended to support successful community reentry. The facilities are expected to incorporate housing, programming, education and vocational functions, medical and mental-health services and other correctional-support infrastructure.

Reentry and rehabilitation are part of the infrastructure strategy

The project is not framed solely around replacement bed capacity. Illinois describes RISE IDOC as an effort to create safe, accessible and restorative correctional environments while strengthening rehabilitative opportunities through education, programming and innovation.

CDB project materials also identify occupational training, educational and vocational partnerships, workforce development and reunification programs as components supporting reintegration into the community and reentry initiatives.

The state says the new facilities are intended to address system-wide needs that include an aging population in custody, increased mental-health demands, trauma-informed design and gender responsiveness.

Implementation signal Illinois is embedding reentry, workforce preparation, behavioral health and rehabilitative programming into the physical design strategy of the new facilities. That makes the procurement relevant to a wider implementation ecosystem than conventional correctional construction alone.

The procurement reaches into the wider corrections vendor ecosystem

The immediate competition is for the Progressive Design-Build Entity rather than for every individual technology, service or equipment package that may ultimately be required. The RFQ nevertheless establishes a project environment extending well beyond conventional building construction.

Its scope includes medical and mental-health environments, education and vocational spaces, correctional programming, security systems and digital project delivery. The RFQ also addresses security electronics, commissioning, project-management information systems, digital delivery and asset-information management.

The RISE IDOC program will use Autodesk Forma as its centralized digital environment for multidisciplinary coordination, project controls, documentation, workflows, design coordination, collaboration, reporting and decision tracking, according to the RFQ.

Justice-market significance The scale and technical breadth suggest potential downstream subcontracting, supplier and specialized-systems opportunities as the selected design-build team develops the project. Those potential opportunities should be distinguished from the current RFQ, which is specifically selecting the lead Progressive Design-Build Entity.

One Progressive Design-Build Entity will lead both facilities

CDB intends to contract the two facilities through one Progressive Design-Build Entity. The state will evaluate qualifications, develop a shortlist and then evaluate additional finalist materials before interviewing and selecting a PDBE.

The RFQ anticipates multiple guaranteed maximum price packages as design and preconstruction progress. CDB says this structure is intended to support schedule efficiencies through early-release packages while maintaining the overall target budget.

Swipe horizontally to review the procurement timeline.

MilestoneDate / status
RFQ publishedAugust 6, 2026
CDB general vendor outreachAugust 26, 2026
RISE IDOC RFQ informational meetingAugust 27, 2026 · 10:00 a.m.–12:00 p.m. CT
Statements of Qualifications dueSeptember 25, 2026 · 2:00 p.m.
Estimated project duration48–60 months following authorization to proceed
RFQ issuedAug. 6, 2026
Vendor outreachAug. 26–27
SOQ deadlineSept. 25 · 2:00 p.m.
Project delivery48–60 months*

*The RFQ estimates project duration at approximately 48–60 months following authorization to proceed.

What vendors should watch next

The near-term checkpoints are the August 26 general outreach event, the August 27 RFQ informational meeting and the September 25 SOQ deadline. Firms considering participation should review CDB’s prequalification requirements and the RFQ directly rather than relying on summaries of eligibility or submission requirements.

For the wider corrections-services and justice-technology market, selection of the Progressive Design-Build Entity will be an important later-stage checkpoint because that team will sit at the center of design, construction, systems integration and subcontracting for the two-facility program.

With approximately 1.5 million square feet contemplated across the preliminary facility programs and approximately 2,300 initial beds, the procurement represents a major multiyear corrections-infrastructure program with direct intersections across behavioral health, education, workforce preparation, reentry-oriented programming and secure institutional technology.

Official sources

OACRA service infrastructure

Explore Illinois reentry and community resources

OACRA organizes public-facing service information across housing, employment, treatment, community service and other reentry-support categories. Directory access is informational and does not determine provider acceptance, government approval or eligibility.

Find Services →
Justice market intelligence

Track procurement and implementation signals

OACRA monitors public-sector funding actions, procurement activity, supervision technology, reentry services and other implementation developments across the justice ecosystem.

Explore Justice Market Intelligence →
Institutional partnerships

Support independent justice intelligence

OACRA works with institutional sponsors and partners supporting independent access to justice policy, service and market intelligence. Sponsorship does not determine editorial coverage or conclusions.

Institutional Sponsorship →

Editorial note: OACRA News & Policy Review is published by OACRA LLC, an independent private organization. OACRA is not a government agency and is not affiliated with or endorsed by the State of Illinois or the agencies covered. Procurement amounts, project scope, dates and status in this article are based on official Illinois Capital Development Board materials reviewed August 24, 2026. Interested firms should rely on the official RFQ and CDB procurement page for current requirements, amendments and deadlines.

Continue with OACRA

Follow the development beyond this report

OACRA connects source-backed reporting with ongoing justice-market intelligence, public-service discovery and institutional participation.

Justice Market Intelligence Track funding, procurement and implementation

Follow solicitations, amendments, awards, contracts, justice technology, supervision systems and service-market developments.

Explore Market Intelligence →
OACRA News Return to the News & Policy Review

Browse current reporting across corrections, reentry, community supervision, funding, policy and implementation.

View OACRA News →
Institutional sponsorship Support independent justice intelligence

Institutional sponsorship helps sustain independent access to OACRA's justice policy, service and market intelligence.

Institutional Sponsorship →
Institutional partnerships Work with OACRA

Explore institutional relationships involving public information, resource infrastructure, research and justice-system intelligence.

Partnerships →

Editorial independence: OACRA News & Policy Review is published by OACRA LLC. Sponsorship and institutional relationships do not determine editorial coverage, sourcing or conclusions.

← OACRA News
Next
Next

California Community Reinvestment Funding